Eltham
WSUD Design & Construction
Linked Harvesting Networks

Eltham Corridor Stormwater Harvesting Network

City of Nillumbik

The Eltham Corridor Stormwater Harvesting Scheme explored whether cost efficiencies can be realised if a number of demands (for irrigation of multiple ovals located along the waterway corridor) and storages and stormwater treatment sites are linked together as a network.  The first project phase modelled the distribution of treated stormwater supply and reuse demand characteristics and further investigated locations for treatment, storage and distribution arrangements considering land ownership and utility locations. 

This first project phase included preliminary civil design of treatment wetlands, other high level infrastructure descriptions, costs performance assessments and optimisation. The cost performance was determined for variations of a network and compared to that of the same elements arranged as a series of individual harvesting projects.  The preferred infrastructure arrangements were identified for further investigation as project phase two where functional design descriptions and subsequent economic analysis will be undertaken.

Water Sensitive City Outcomes:

  • passive and active irrigation of the urban landscape
  • multiple beneficial outcomes
  • holistic cost-benefit appraisal

Retrofit Solutions

Allgas Street Stormwater Disconnection and Riparian Rehabilitation

WSUD for Schools

St Gregory’s College Water Sensitive Urban Design

WSUD for Public Realm

Western Precinct Raingarden and Wetland Design

Stormwater Treatment Design

Bellvista Estate Streetscape WSUD

Urban development solutions

Everley Estate Multifunctional WSUD Assets

Stormwater Harvesting for Open Space Irrigation

Royal Park Wetland and Stormwater Harvesting System

Integrated Community Water Planning

Sydney Science Park Integrated Water Design

Innovative wetland design

Torhaven WSUD and Stormwater Treatment Ephemeral Wetland

Stormwater Harvesting

Elsternwick Park Stormwater Harvesting

Flood Mitigation

Elizabeth Street Catchment Flood Risk Reduction Study

Large Scale Alternative Water Supplies

Toolern Integrated Water Cycle Management Strategy Designs

Permeable Paving Testing

Infiltration Testing for Permeable Pavement Systems

Priority Stormwater Treatment and Harvesting Design

Priority WSUD Projects: Gordon Barnard Reserve and Macleay Park

Asset Maintenance

Streetscape WSUD Asset Auditing, Maintenance and Rectification

Passively irrigated trees

Upper Mary Street Revitalisation

WSUD for Residential Developments

Harcrest Residential Development

WSUD for New Development

Sunbury Hills WSUD Strategy

Stormwater harvesting

Alma Park Stormwater Harvesting Scheme

Channel naturalisation

Small Creek Naturalisation Stages 1, 2 & 3